There are three proposed windfarm sites by ScottishPower. East Anglia Windfarm One, Three and Four.Windfarm. EAW1 has been approved. EAW3 is in final planning and approval stages.
I understand EAW1 will start in January 2017 in the landfall site in the field to the east of Ferry Road, immediately south of the landmark path. It seems that most of this field will be used by ScottishPower for what’s called the transition pit site. This is where the sea cables join the land cables that will be trenched for 23 miles across the countryside to Bramford. The cables will pass under the River Deben, under the East Coast railway line, A12, A14, River Gipping before reaching Bramford.